Chancellor Park Stage 17

Location: Sippy Downs, Queensland
Date: January 2003 - January 2004
Client: Chaltara Pty Ltd
Engineers: W P Brown & Partners

Hall Contracting undertook the construction of Stage 17 of this ongoing subdivision during 2003.


A total of approximately 180 lots were constructed in this stage with an adjoining recreation park area created as part of the works.

Extensive earthworks and open drains were required to be constructed due to the flat terrain and tight drainage tolerances.