Cullen Bay Dredging - NT
Dredge: Everglade 14”
Client: NT Government
Dates: Mar - May 2008
Hall has completed the dredging of 90,000m3 sand and silts from
Cullen Bay, in Darwin. The material was pumped via a pipeline anchored
to the seabed 1km out into the main channel. Working in tidal flows
of 4 to 6 knots, the project was completed ahead of schedule and
incident free.
: : back to
projects. |
|
|