Gladstone Marina Dredging
Dredge: Mabuiag
Client: Gladstone Ports Corporation Ltd
Dates: April-June 2009
Hall Contracting was contracted to carry out maintenance dredging of the Gladstone Marina. The project involved removal of an initial 150,000 cubic metres of sediment to restore the Marina to -4m.
CSD Mabuiag was utilised 24 hours a day, 6 days a week to carry out the project.