Glenelg Safe Harbour
Location: Adelaide, South Australia
Approx. Total Project Value: $6 million
Dredge: Kikilu 14"
Completion: August 1997
Engineers: Connell Wagner, Adelaide

Changing Cutter Heads on "Kikilu".
This project required approximately 180,000 m3 of sand, calcrete,
river gravel and clay to be dredged to provide a harbour for the
new kangaroo island ferry. Three booster stations were required
to push the clay and rock approximately four kilometres to the
pit.
|